Texas Gov. Greg Abbott sent a letter Aug. 3 to Public Utility Commission of Texas Chairman Thomas Gleeson and Electric Reliability Council of Texas Chief Executive Officer Pablo Vegas directing the PUCT and ERCOT to conduct a “comprehensive verification and audit of all data centers advancing through ERCOT’s interconnection process[.]”
The audit must occur “before any additional data centers are approved to move forward” and will apparently review each project’s compliance with applicable requirements set by PUCT, ERCOT and state law. Any project found to be in violation of such requirements, according to the letter, “must be denied connection to the Texas grid.”
The letter stated that ERCOT is considering approximately 474 gigawatts of requests, 90 percent of which are data centers. The letter further indicated its purpose is “[t]o keep the grid stable and reliable” — specifically noting an alleged failure of some data centers to comply with the PUCT’s recent survey of water and power usage.
ERCOT on Aug. 10 filed a request for good cause exceptions that would allow it to extend several deadlines associated with its implementation of the so-called “Batch Zero” load interconnection process (for loads 75 megawatts and above) to accommodate the governor’s directive. The filing also provides a preview of how ERCOT intends to handle the audit process. Discussion at the Aug. 14 open meeting provided further information on timing expectations.
Below, we outline the primary requirements of the directive, as well as ERCOT’s proposed plan to accommodate the audit requirements, and analyze the key impacts on data centers currently seeking to interconnect to the ERCOT grid.
Audit Information Requested
In addition to verifying and auditing compliance with existing requirements, the directive also specifically asks PUCT and ERCOT to obtain additional detailed information from each data center project on the following topics:
- Financial incentives. The extent to which data centers are paying their own way or relying on state and local tax incentives, grants, abatements or other public financial assistance.
- Power sourcing. Whether data centers are providing their own power or depending on the ERCOT grid, including projected annual and peak electricity consumption and progress toward constructing or procuring on-site generation.
- Water usage. Projected annual and peak water consumption, anticipated water supply sources and cooling technology to be used (air-cooled, closed-loop or other water-efficient systems).
- Community impact mitigation. Measures to reduce impacts on neighboring property owners and communities, including noise mitigation, light controls, setbacks, traffic improvements and emergency response coordination.
- Ownership and control. Details regarding the ownership and controlling interests in the project. Specifics on how detailed information on corporate structure needs to be was not provided with the letter.
Under the directive, any data center project that fails to comply with the verification and audit process “must be denied” interconnection to the grid. The letter does not provide any timeline on which the audit must be conducted.
While the directive seeks to verify and audit compliance with existing requirements and to obtain information on community impacts, it is not a moratorium on data center development.
ERCOT’s proposed plan and key impacts to data centers
ERCOT’s Aug. 10 filing requested exceptions to certain of ERCOT’s own deadlines related to Batch Zero and also previewed ERCOT’s plan to implement the audit. At the Aug. 14 open meeting, ERCOT stated it expects the verification process to take several months, but less than nine months.
Based on the directive and ERCOT’s initial filing and open meeting comments, the key impacts to data centers seeking to interconnect to ERCOT are likely to be as follows:
Key Impact #1: Delays to certain Batch Zero deadlines; temporary pause in studies
The immediate practical impact of the governor’s directive, at least for those loads 75 MW and above seeking to be included as part of the Batch Zero process (large loads), is a delay in ERCOT’s announcing Batch Zero classifications and a “temporary paus[e]” of the study process while the audit is completed. However, there is no imminent impact to the issuance of study results by April 9, 2027 (yet).
ERCOT made the following requests related to specific Batch Zero deadlines in its Aug. 10 filing:
- Request for waiver of the Aug. 7 classification deadline. Under ERCOT Planning Guide requirements, ERCOT was required to classify each large load into one of three categories by the Aug. 7 deadline: (1) load that has already been sufficiently studied for interconnection (base load); (2) load that requires additional study in Batch Zero (studied load); and (3) load that will require study in a future interconnection process. ERCOT explained it originally intended to complete the verification process, which was already a required component of Batch Zero, after communicating classifications and before the April 2027 study results deadline, but that it could not complete the verification process before the Aug. 7 deadline, as the letter would require. As a result, ERCOT requires waiver of the classification deadline.
- Request to include large loads in quarterly stability assessments (QSA) before they are classified as base load. ERCOT requested to include large loads that interconnecting distribution service providers and transmission service providers requested be classified as base load and that ERCOT determined are eligible to qualify as base load but has not yet formally classified in the Aug. 1 and Nov. 1 QSA. This inclusion was originally contemplated to only occur after classification, which will now be delayed. Six large loads are expected to be in the Aug 1 QSA, and 17 large loads are potentially eligible for the Nov. 1 QSA. ERCOT clarified that QSA inclusion would not constitute energization authorization for that particular project.
- Request for waiver to provide Batch Zero dynamic model review and deficiency notifications. ERCOT was required to notify interconnecting large loads by Aug. 7 of any deficiencies in submitted dynamic data, which such loads were required to cure by Aug. 31 or be removed from Batch Zero. ERCOT noted it was unable to complete its review on this timeline given the volume of data received but will do so as quickly as possible. To accommodate this delay, ERCOT requests allowing large loads to cure any deficiency noticed by ERCOT after the Aug. 7 deadline within 24 days of notification.
The following Gibson Dunn lawyers prepared this update: Tory Lauterbach, Adam Whitehouse, Allison Hellreich, Carrie Mobley and Jess Rollinson
Importantly, and as noted above, ERCOT did not request an extension of the April 9, 2027, deadline to provide Batch Zero interconnection study results. In its filing ERCOT noted that it is “working on the scope and timing of the verification process” and that it does not yet know how the delay will impact the study timeline. ERCOT indicated it may request another good cause exception or make changes through the stakeholder process to the study deadline “[i]f necessary.”
Key Impact #2: Responses to ERCOT-issued RFIs regarding compliance and community impact information will be mandatory, although exact timing of the process and scope of the process is not yet known
- Issue requests for information to all large loads in Batch Zero regarding verification of compliance, with these responses used to verify each large load’s attestations submitted earlier this year.
- If ERCOT determines a large load submitted information that is false in any material respect, or if the large load fails to respond, it will be classified as ineligible for Batch Zero.
- If ERCOT determines a large load submitted information that is false in any material respect, or if the large load fails to respond, it will be classified as ineligible for Batch Zero.
- Issue RFIs to obtain the community impact information required by the directive.
- Issue similar RFIs to loads with a peak demand greater than 25 MW but less than 75 MW that are seeking to interconnect but that are not part of Batch Zero.
- ERCOT estimates there are approximately 8,766 MW of such loads that will be impacted.
- ERCOT estimates there are approximately 8,766 MW of such loads that will be impacted.
- Issue periodic updates to the PUCT, and once complete, compile the results into a report filed with the PUCT.
ERCOT plans to submit another filing to the PUCT providing additional details on implementation, will discuss such implementation during the Aug. 20 open meeting and expects to commence its verification and audit process “shortly after” the open meeting.
Key Impact #3: The delays described above will also delay issuance of the long-term load forecast (LTLF)
ERCOT also explained that due to the delays to the classification notifications noted above, the LTLF, which ERCOT had earlier requested to adjust to include Batch Zero base load information, will also be delayed. The LTLF is important to data centers because the inclusion of their projects in the forecasts ultimately influences what physical infrastructure is built to serve their projects. ERCOT had originally anticipated finalizing the LTLF by mid-August 2026. Although the LTLF will be delayed, ERCOT explained that incorporating verified base loads into the forecast “will produce a more accurate and realistic forecast than alternative methodologies[.]”
Victoria “Tory” Lauterbach is a partner in Gibson Dunn’s Washington, D.C. office and co-chair of the Energy Regulation and Litigation practice group. Tory is a leader within the firm’s data centers and digital infrastructure practice, where she advises data center developers, investors, and lenders regarding all aspects of delivering electric power to data centers.

Adam Whitehouse is a partner in the Houston office of Gibson, Dunn & Crutcher, where he advises clients on complex transactions across the energy and power sectors. Adam is a key member of the firm’s Data Centers and Digital Infrastructure practice, where he advises data center developers, hyperscale users, energy producers, and infrastructure investors on all aspects of powering and supplying large-scale data center projects.

Allison Hellreich, Carrie Mobley and Jess Rollinson also contributed to this article.
